Avviso 1/2019 PaIS
The title is the official one, in Italian, as published in the source.
Azienda sanitaria locale Toscana sud est
€37,375 funded, €24,601 already paid.
Data for this project updated to 2026-06-30
The planned end date (2023-10-31) is earlier than the date of the data: deadline passed according to the data.
What it is
- Topic
- Health and social inclusion (Salute e inclusione sociale) (official term: Inclusione sociale e salute)
- Type
- Servizi; Misure di Inclusione sociale-sostegno al reddito
- Responsible body
- Azienda sanitaria locale Toscana sud est
- Declared status
- In corso · phase: Esecuzione fornitura
- Project start
- 2019-09-27
- Planned project end
- 2023-10-31
- Actual project end
- not available
- CUP
- C11B20001240006 (Unique Project Code)
- Cycle
- Ciclo di programmazione 2014-2020
«Not available» means the body did not report that item to the source. The dates above refer to the whole project, as reported by the body. The official OpenCoesione page may instead show the dates of a single phase, for example the execution of works, which can differ: the phases are listed below.
Where the money comes from
- Italian State: €37,375
Official description (Italian)
Rafforzamento dei servizi territoriali per l'attuazione dei Patti per Inclusione Sociale (PaIS) in continuità con Avviso 3/2016
Declared phases
| Phase (Italian) | Planned start | Actual start | Planned end | Actual end |
|---|---|---|---|---|
| Stipula Contratto | 2019-09-27 | 2019-09-27 | 2021-04-30 | 2021-04-30 |
| Esecuzione Fornitura | 2022-01-03 | 2022-01-03 | 2023-10-31 | not available |
Source
Official page on OpenCoesione See where this data comes from (JSON)
The «data» link is the exact API response used for this page. To learn how to read it: Tutorial.