Cassa di espansione Torrente Bicchieraia
The title is the official one, in Italian, as published in the source.
ConclusoEnvironment (Ambiente)Public works (Lavori pubblici)
Regione Toscana
€2,313,383 funded, €2,268,154 already paid.
Data for this project updated to 2026-06-30
€2,313,383
Funded€2,268,154
Already paid (98% of the funded amount)What it is
- Topic
- Environment (Ambiente) (official term: Ambiente)
- Type
- Lavori pubblici; Regimazione acque
- Responsible body
- Regione Toscana
- Declared status
- Concluso · phase: Collaudo
- Project start
- 2015-04-06
- Planned project end
- 2014-07-30
- Actual project end
- 2021-07-01
- CUP
- J17B15000520003 (Unique Project Code)
- Cycle
- Ciclo di programmazione 2014-2020
«Not available» means the body did not report that item to the source. The dates above refer to the whole project, as reported by the body. The official OpenCoesione page may instead show the dates of a single phase, for example the execution of works, which can differ: the phases are listed below.
Where the money comes from
- Italian State: €1,619,368
- Region: €694,015
Declared phases
| Phase (Italian) | Planned start | Actual start | Planned end | Actual end |
|---|---|---|---|---|
| Studio di fattibilita' | 2014-06-30 | 2014-06-30 | 2014-07-30 | 2014-07-30 |
| Progettazione preliminare | 2014-06-30 | 2014-06-30 | 2014-07-30 | 2014-07-30 |
| Progettazione definitiva | 2015-04-06 | 2015-04-06 | 2015-05-06 | 2015-05-06 |
| progettazione esecutiva | 2016-06-01 | 2016-06-01 | 2018-04-06 | 2018-04-06 |
| Aggiudicazione gara | not available | 2018-04-13 | not available | not available |
| Stipula contratto | 2019-02-06 | 2019-02-06 | 2019-04-11 | 2019-04-11 |
| Esecuzione lavori | 2019-05-03 | 2019-05-03 | 2021-07-02 | 2021-07-01 |
| Collaudo | 2021-07-02 | 2021-07-02 | 2022-07-01 | 2022-06-28 |
Source
Official page on OpenCoesione See where this data comes from (JSON)
The «data» link is the exact API response used for this page. To learn how to read it: Tutorial.