Convenzione operativa RT-MISE del 27/05/2016
The title is shown in Italian, rewritten in plain Italian from the official title and summary. Original official title: «(A19_2016_CSP004) Convenzione operativa RT-MISE del 27/05/2016»
Infratel Italia SPA; Mimit - ministero delle imprese e del made in Italy
€12,102,670 funded, €12,102,670 already paid.
Data for this project updated to 2026-06-30
What it is
- Topic
- Digital services (Servizi digitali) (official term: Reti e servizi digitali)
- Type
- Lavori pubblici; Altre Opere ed impianti per telecomunicazione
- Responsible body
- Infratel Italia SPA; Mimit - ministero delle imprese e del made in Italy
- Declared status
- Concluso · phase: Collaudo
- Project start
- 2016-05-28
- Planned project end
- 2019-01-28
- Actual project end
- 2024-10-07
- CUP
- B57D16000040006 (Unique Project Code)
- Cycle
- Ciclo di programmazione 2014-2020
«Not available» means the body did not report that item to the source. The dates above refer to the whole project, as reported by the body. The official OpenCoesione page may instead show the dates of a single phase, for example the execution of works, which can differ: the phases are listed below.
Where the money comes from
- European Union: €6,051,335
- Italian State: €4,235,935
- Region: €1,815,401
Official description (Italian)
Convenzione operativa RT-MISE del 27/05/2016
Declared phases
| Phase (Italian) | Planned start | Actual start | Planned end | Actual end |
|---|---|---|---|---|
| Studio di fattibilita' | 2017-06-19 | 2017-06-19 | 2017-06-19 | 2017-06-19 |
| Progettazione preliminare | 2017-06-19 | 2017-06-19 | 2017-06-19 | 2017-06-19 |
| Progettazione definitiva | 2017-06-19 | 2017-06-19 | 2021-12-31 | 2022-12-31 |
| progettazione esecutiva | 2017-07-19 | 2017-06-19 | 2022-06-30 | 2023-02-28 |
| Aggiudicazione gara | not available | 2016-06-03 | not available | 2017-05-15 |
| Stipula contratto | 2017-06-19 | 2017-06-19 | 2017-06-19 | 2017-06-19 |
| Esecuzione lavori | 2017-10-01 | 2017-10-01 | 2022-12-31 | 2023-06-30 |
| Collaudo | 2018-04-30 | 2018-04-30 | 2023-03-31 | 2023-09-30 |
Source
Official page on OpenCoesione See where this data comes from (JSON)
The «data» link is the exact API response used for this page. To learn how to read it: Tutorial.