Cogeneratore ad alto rendimento Campostaggia

The title is shown in Italian, rewritten in plain Italian from the official title and summary. Original official title: «(10360.14072017.115000006) Cogeneratore Alto Rendimento Campostaggia»

ConclusoEnergy (Energia)Public works (Lavori pubblici)

Azienda sanitaria locale Toscana sud est; Cpl concordia soc.Coop

€1,133,392 funded, €1,133,392 already paid.

Data for this project updated to 2026-06-30

€1,133,392
Funded
€1,133,392
Already paid (100% of the funded amount)

What it is

Topic
Energy (Energia) (official term: Energia)
Type
Lavori pubblici; Impianti di cogenerazione
Responsible body
Azienda sanitaria locale Toscana sud est; Cpl concordia soc.Coop
Declared status
Concluso · phase: Collaudo
Project start
2018-11-16
Planned project end
2020-11-16
Actual project end
2022-08-02
CUP
C59J18000110002 (Unique Project Code)
Cycle
Ciclo di programmazione 2014-2020

«Not available» means the body did not report that item to the source. The dates above refer to the whole project, as reported by the body. The official OpenCoesione page may instead show the dates of a single phase, for example the execution of works, which can differ: the phases are listed below.

Where the money comes from

Official description (Italian)

REALIZZAZIONE DI UN IMPIANTO DI COGENERAZIONE DI ENERGIA ELETTRICA E TERMICA A SERVIZIO DELL'OSPEDALE DI CAMPOSTAGGIA, SITO NEL COMUNE DI POGGIBONSIL'INTERVENTO NON E' RIPARTITO IN LOTTI FUNZIONALI

Declared phases

Phase (Italian)Planned startActual startPlanned endActual end
Studio di fattibilita'2017-08-092017-03-282017-11-152017-10-16
Progettazione preliminare2017-08-092017-03-282017-11-152017-10-16
Progettazione definitiva2017-08-092017-03-282017-11-152017-10-16
progettazione esecutiva2017-08-092017-04-102017-11-152017-10-16
Aggiudicazione garanot available2019-03-05not availablenot available
Stipula contratto2019-08-292019-08-292019-08-292019-08-29
Esecuzione lavori2019-01-152019-10-102020-04-152020-12-03
Collaudo2020-07-152021-03-022020-07-152021-03-02